The Commercial Case Law Index is a collection of judgments from African countries on topics relating to commercial legal practice. The collection aims to provide a snapshot of commercial legal practice in a country, rather than present solely traditionally "reportable" cases. The index currently covers 400 judgments from Uganda, Tanzania, Nigeria, Ghana and South Africa.
Get started on finding judgments that are relevant to you by browsing the topic list on the left of the screen. Click the arrows next to the topic names to reveal a detailed list of sub-topics. Most judgments are accompanied by a short summary written by subject-matter expert postgraduate students from the University of Cape Town.
The case was an application seeking to revive a consent judgment set aside by the registrar of the court.
The dispute emanated from an application by the respondent seeking an order to nullify registration of property in the name of the defendants (who are now applicants). The order was granted under an ex parte application because the respondents failed to respond to the suit. The respondents tried without success to appeal the judgment.
The respondents then filed a notice of appeal to the Appeal Court seeking to appeal against the order of the High Court dismissing the application. They also requested an interim order for stay of execution. The applicant (who is now the respondent) objected to the appeal arguing that it was late which was confirmed by the registrar. The respondents referred the matter to a single judge and pending the determination by the judge, the parties entered into a consent judgment which was endorsed by the registrar. The registrar later set aside the consent judgment which the applicants are now seeking to revive.
In deciding the case, the court held that there was no appeal before the single judge because the applicants filed the appeal late. The court ruled that the registrar has no jurisdiction to hear and dispose an appeal. It found that the registrar erred when he entered a consent judgment on a matter which was on appeal before a court. It further ruled that the consent judgment was null and void thus it cannot be revived.
The plaintiff applied to the court to enter judgment on admission for the plaintiff because the defendant materially admitted all the facts; and that the court should only be addressed on the issue of general damages and costs.
The court concluded that since the defendant in this case agreed to and admitted all the material facts in the plaintiff’s claim, there remained no other triable issues for the court to consider.
A ‘triable issue’ was defined as an issue that only arises when a material proposition of law or fact is affirmed by the one party and denied by the other; however the parties are bound by their pleadings and cannot be allowed to depart from them.
The court held that an admission has to be clear and unambiguous and must state precisely what is being admitted. Once an admission of facts is made, court may upon application make such order or file such judgment.
It is against this backdrop that the judgment on admission was entered.
The plaintiff filed an action against the defendant for breach of contract, special damages, general damages, interest and costs of the suit. The two issues were whether there was a legally binding contract for decorating services between the plaintiff and the defendant and whether the plaintiff is entitled to the remedies claimed.
It was submitted that under s 55 of the Public Procurement and Disposal of Public Assets Act 2003 (PPDA or the act) all public procurement has to be carried out in accordance with the rules set out in the act and regulations and guidelines made under the act. The court held that there was non-compliance with the PPDA regulations on procurement of services.
The court stated that the act was established to ensure the application of fair, competitive, transparent, non-discriminatory and value for money procurement and disposal standards and practices. Although there was non-compliance with established procedures as set out above, the contracts committee subsequently agreed with the methodology chosen albeit after the event. They ratified the process.
The court went on to decide that on the first issue thereof of whether there was a legally binding contract for decorating services between the plaintiff and the defendant, that the permanent secretary upon clearance by the Contracts Committee was under obligation to retrospectively regularise the procurement of the services of the plaintiff representing a consortium of companies which carried out decorations. The failure to regularise the procurement of the services of the plaintiff worked injustice because the plaintiffs remained unpaid for services procured and which had been cleared by the Contracts Committee.
Each of the parties accused the other of breach of contract. The plaintiff alleged breach in terms of non-payment for services conducted. The defendant counter-claimed breach in terms of failure to comply with the set completion time and providing substandard quality work.
The defendant also contended that should it be found liable, it should be indemnified by a third party as it has been negligent in doing its work.This court held that the defendant is not entitled to indemnity or any contribution from the third party.
The court found that there was no breach of contract by the plaintiff in so far as completion time is concerned. The defendant waived the right to complain about completion time and was estopped from raising the issue. The defendant was found to not be entitled to monies claimed in the counterclaim, as there was no basis for it and this court had already held that the defendant waived its rights.
The plaintiff was found to be entitled to the monies reflected on two certificates. The plaintiff was not awarded the contractual interest claimed because the court held that the the defendant was justified in not paying contractual interest for an erroneously issued certificate.
Following its non-payment for construction services rendered, the plaintiff sued the defendant for breach of contract. A counter-claim was lodged alleging that the plaintiff breached the parties’ agreement through a significant delay in performance and sub-standard discharge of its obligations. Insofar as the third party had issued unqualified certificates of completion for the plaintiff’s/counter-defendant’s alleged malperformance, the defendant/counter-claimant contended that it was negligent and therefore liable for a degree of indemnification.
The defendant/counter-claimant was found to have impliedly waived its right to liquidated damages for late performance and consequently estopped from enforcing it. The court found further that the plaintiff’s/counter-defendant’s performance, while flawed in some respects, was not materially defective. The issuing of a certificate of completion marks the close of liquidated damages liability and commences the period of defects liability, where errors in performance are identified and submitted to the contract debtor for rectification. Failure to rectify does not give a right to sue for breach but rather gives the employer the right to refuse to release retention monies.
The third party was found to have conducted its work competently, barring one erroneously issued certificate, and was under no obligation to indemnify the defendant. The defendant was therefore indebted to the plaintiff for the outstanding amounts stipulated by the lawfully issued certificates. Because the defendant had accepted and made use of the plaintiff’s performance, despite the erroneously issued certificate of completion, the court found that it was liable to compensate the latter under the law of unjustified enrichment. Judgment was entered for the plaintiff with costs.
The matter dealt with an application for foreclosure and sale of mortgaged property as a result of failure to make loan repayments by defendant.
The main issue was whether the plaintiff could exercise its right to foreclose the property. The court cited s 8(1) of the Mortgage Act that allows one to redeem the property at any time of breach and or to get a court order effecting the redemption. Reference to How v Vigures was also made regarding the triggers for foreclosure proceedings as being when due payment has not been made on date for redemption (default) or when there is a breach of any terms of the mortgage.
The court established that as the defendant had not complied with the terms of the credit facility agreement by not paying the agreed monthly instalments for a period of two years despite repeated demands, the exercise of the right to foreclosure was held to be fit and proper.
The court therefore concluded that the plaintiff could exercise the right to foreclose and accordingly allowed the application.
In this case the defendant raised a preliminary objection to the suit on grounds that the suit is time barred and that the High Court of Uganda has no jurisdiction to try the suit. The court stated that it could not decide on the issue of time until it makes a determination on whether it could exercise its jurisdiction in the matter. The court relied on article 139 of the Constitution and the rule that a contract cannot oust the jurisdiction of the high court and held that a clause to submit to the exclusive jurisdiction of the foreign court is enforceable by the High Court. However, the court stated that the jurisdiction of the court in such circumstances is subject to the plaintiff justifying the filing of the action in Uganda, for instance by proving that the defendant was using the exclusive jurisdiction clause to avoid liability. The court was satisfied that the plaintiff in this case had failed to do so. Accordingly, the court enforced the terms of the contract, sustained the preliminary objection and dismissed the suit with costs.
This case considered the instance when the veil of incorporation can be lifted. The mind of a company where guilty intent or responsibility is being considered cannot be separated from the minds of the directors. The corporate veil ought to be lifted where there is proof of involvement of the directors in fraud. Once there has been an allegation of fraud against the company, the directors are ay virtue alleged to be involved. Accordingly, the veil of incorporation will be lifted where it is proved that the directors, acting as the mind and body of the company were involved in an act of dishonesty.
The plaintiff sued the defendant for breach of contract following its failure to pay in full – inclusive of VAT and penalties accruing from delayed payment – for construction services rendered. Two clear issues arose: whether the plaintiff was entitled to the sum claim and what remedies were available to the litigants. The contract provided for specific procedures in the event of disputes between its signatories. The plaintiff’s grievances with the project manager’s final certificate (which confirmed the amount owing by the defendant) ought to have been aired via these channels, so the defendant could be alerted thereto.
Because timeous and effective payment was based on certificates, the court found that the defendant could not be held liable for non-payment exceeding the certified amount. The court accordingly reduced the sum claim. Because the defendant had hampered the plaintiff’s commercial endeavours through its breach, it stood liable for general damages. The plaintiff provided no elucidation on the quantum thereof, and so its determination fell to the court’s discretion.